      1. Discussion on PR : https://github.com/RackHD/on-http/pull/621 regarding Redfish events from the Dell r630 for Symphony Call Home Workstream. 
        1. The PR was merged on Friday after Former user (Deleted) removed the request for changes.    
        2. The documentation PR has not yet been merged (https://github.com/RackHD/docs/pull/385).  Request from Former user (Deleted) to mark this as "experimental".  What is the team consensus on that?  No issues for using experimental.
        3. Since the email thread was lengthy, are there specific changes that need to be addressed in the short or long term?  If so, what are they?
      2. UPDATE for philosophical differences it shouldn't take more than 24 hours to come to a conclusion.   Anchor and PO will make sure that if the changes are too drastic (impact other customers) they will look to CC for guidance (send email about the changes) otherwise if not then Anchor and PO can approve the merge without waiting on full approval from the CC.   Anchor and PO can overrule the -1 from other CC, conversation can be had later to talk about why but Anchor and PO have an immediate need to get it to customer and thus making the decision based on the customer need/expedience. 
      3. Discuss version bumping
        1. https://hardware.corp.emc.com/pages/viewpage.action?pageId=99942703
      4. RAC-4784 - Getting issue details... STATUS  P1 blocking the latest release.
      5. Brian Parry working on a complete solution and possibly will close PR 625 as not needed.
            AI Peter Pan to add docker build to the PR Gate