Attendees

Goals

  • This meeting is to prepare and provide OSE initiatives input from all team meetings for OSE Governance.

...

Time

Item

Who

Notes


Maglev BlockersLeo Zhang
  • No Blockers
  • PR gate failure rate is high - CI/CD stability - continue to work (Still have a high rate of failure) - still studying root cause
  • Platform-W successfully ESXi 6.5 installed, FW upgrade in process
  • MRES - dev ops automation use caseidentified areas for improvement
  • Upgrade to latest InfraSIM? - discuss at end of meeting
  • Platform-W - Focused on FW upgrade in process - PR for Warnado skill pack, need merge from Jeanne
  • Secure erase on Dell - try to test using InfraSIM

Mustangs BlockersFormer user (Deleted)Not available
  • No Blockers
  • This week all micro services should be checked in
  • Containers drag in allot of other code and need to get legal approval - Target next week
  • Mustang Block Island RIs should be closed by end of week

Longhorn Blockers

Not available

  • Mustang team will merge PRs by end of week

Corsair BlockersFormer user (Deleted)
  • No Blockers
  • Tim to review videos for Dell EMC world
  • ECS cannot install on real hardware now working
  • Working on CoprHD on real HW cannot see ScaleIO nodes
  • More resources added to CIT/FIt
  • RackHD slack channel open a JIRA ticket - online
Stryker
  • - bug identified and fixed
  • Trello board for affinity exercise - for prescope of asset monitor and @scale testing

Veyron BlockersAmy Mullins
  • No Blockers
  • DSS 9000 doneBlockers
        • Latest docker image is failing taskgraph
  • RAC-4964 issued for testing secure erase
  • Stryker and Gripen converged into Veyron
  • Ansible playbooks needed RI being developed
  • Symphony RCM Team asking for help
  • Temp DOJO set up in 171 Upper mezz, 176 be a couple of months

Gripen Scrumwagon BlockersAmy Mullins
  • No Blockers
  • Waiting on Symphony RCM architects
  • DSS-9000 / shovel open stack integration - Video demo - Looks great - Dell EMC code booth at open stack summit next week
  • Moved to Temp DOJO
Scrumwagon BlockersAmy Mullins
  • No Blockers
  • Moved to Temp DOJO
  • Gary White presentation on pair programming
  • James at openstack summit

Core CommittersFormer user (Deleted)
  • No Blockers
  • 1 week releases and sprints - starting from May 8
  • Have teams review RackHD merge guidelines - in reviewApproved will be published
  • Unique IDs for nodes not able to use BIOS GUID OVA - How do we store them - daily build to external Artifactory, releases to Bintray- target two weeks
  • Are we properly using Bintray - too much, too often - Leo to discuss with Peter
  Quality Board Amy Mullins
  • No Blockers
  • Something incorrect in master CI - still running
  • RAC-4729 P1 CI / CD stability
    • More meetings - more frequent release?, external mirrors, notification, and otherStill working
    • Externally visible content - still discussingshort term and long term plan in place

ESM / Asset monitor
  • Joint EOS access monitor daily stand ups this week - only update what is in the lab now
  • Possible end of May Round Rock meeting - show them what RackHD can do

Product Management / Backlog RefinementTom Capirchio
  • Not AvailableBlockers -

WebUI
  • Web UI has a bunch of bugs
  • Demo cleaned up but WebUI (no work at this time, (Meglev will do minimal support to keep up to date(Lyne Lin) needs work Tom Capirchio ProductionNow - ProductionNow Trademark discouraged according to legal / marketing - Veyron will assist with customer fixes
  • Tim Larson EDG Ui (Clarity) followup - Looking at what can be opensourced
  • What is an RI - any external consumable feature and tools that is checked into OSE repos
  • New RI needed to develop a RackHD Bootcamp video to get new users started

Other - Monorail tickets redistribution?
Tom will send out email to Tom Cap

Other - Knowledge Database and Design specsTom S

No action to date, after Dell EMC World - email set by Tom Sullivan for design doc location. CorpHD process identified.

  • "How to" documents will be brought into the confluence database.
  • RI design docs will be released in conjunction with the feature video. The document can be attached to the RI or stored in and linked to https://rackhd.atlassian.net/wiki/x/B4CH. The design doc is meant to be a snap shot at the time the feature is released and will not evolve.

Other - RackHD usabilityMustangNeed to simplify the barrier of entry including the RackHD demo

Other - Video demosTom SInside Dell now, looking at EDUTUBE.

Other - EquipmentAmy

Need more equipment for test equipment -sharing dev and test -Is there budget ,< $25 K, need for regression (CI / CD) Amy Mullins will put together a formal request to Tim Larson

Thomas Sullivan look into inventory, Tim Larson look at free equipment from Cisco.

@scale test environment being decommissioned, get equipment for Maglev Team. - Amy Mullins


Action items

  •  Still cannot download tools from the internet, can get to Cisco switches but need more, will work with Former user (Deleted) - external sites from the dev system Amy Mullins to followup with Brenda.
  •  Tom Capirchio ProductionNow - Trademark followup need for Dell EMC world - Not advised to trademark by legal
  •  Tim Larson EDG followup - Looking at what can be opensourced
  •  Solution pack find a consumer Tom Capirchio meeting today - 4/5
  •  Thomas Sullivan Add multi stockholder field
  •  Self service release notes, need also a internal SW checklist generated - Thomas Sullivanto discuss offline with Amy Mullins
  •  $25 K, need for regression (CI / CD) Amy Mullins will put together a formal request to Tim Larson
  •  Thomas Sullivan look into Cisco inventory, 
  •  Tim Larson look at free equipment from Cisco.
  •  @scale test environment being decommissioned, get equipment for Maglev Team. - Amy Mullins
  •  RackHD passwords and username complexity, Tom Capirchio will reevaluate.

...