- Shanghai (Maglev - Leo):
- Holiday is starting
- Need US team to back up the sprint rel process
- Need to get Maglev team PRs approved before they go on Holiday
- Texas (Mustang - Maithri)
- Have the power requirements gathering is complete
- Redfish poller completed
- Clarity UI – in progress
- Micro services using swagger in progress is complete - pending review from Jon
- NextB scan done came back clean - need to verify all the open source licenses this week
- Minnesota (Corsair - Rod):
- No Blockers
- FIT phase 1 complete
- FIT phase 2 in progress - new bells and whistles
- Solution packs - Started work
- Test page draft is running (TAAS) - Engage open source to enable test - complete in a couple of sprints
- A customer account feature (LDAP) - want to use RackHD - Tom Cap needs to discuss with customer representatives
- HA stories still in progress
- Amy:
- Blockers:
- Debian restoration not complete - still issues - time consuming - What are we trying to restore - Move to Core Committers discussion
- New UCS service repo - who has permissions - Get core committer permissions
- Quality review board - 3 bugs with one possible P1 - Discuss at CC meeting
- Data migration model needs input - change by end of sprint
- Stability of Dell 14G (R640) early prototype material - need entrance criteria for prototype material
- New hardware to build and test to introduce hardware as a quality gate
- Working on RI-113 “Redfish 2016.3 Schema Implementation”
- Symphony kickoff - scoping this morning - Dell EMC world demo
- Blockers:
...